Contract Package 017661 – CE5457 Potlines 1 & 2, UAE

Client: Emirates Aluminium Company Limited (EMAL)
The smelter complex covers a site of 6 sqkm and was built in two phases. Phase I was completed in early 2011, ahead of schedule. In 2011, EMAL commenced the Phase II expansion which was completed by the end of 2014. At the end of Phase II, EMAL will have the longest single potline in the world at 1.7 km and annual production capacity will almost double to 1.3 million metric tonnes…

Paper Mill Project – Phase 1 & 2, UAE

Client: ADNIP, Abu Dhabi
Electrical, Mechanical and Instrumentation Works related to Tissue Paper Mill including Design, Supply and Installation of Effluent Water Treatment Facility Similarly for Phase 2, scope of works included Complete Mechanical, Electrical & Instrumentation Erection Works associated with 36,000 Ton/Yr Paper Mill and 80 Ton/Day De-Inking Plant.