This 380/132/33/13.8KV BSP at AL- WAJH , Saudi Arabia was constructed by Danway EME on Turnkey basis. Scope of works includes Engineering, procurement, Installation, Testing & Commissioning of complete Substation which includes , 15 bays of 380kV GIS, 2 bays of 380 kV HGIS ,21 bays of 132kV GIS, 23 bays of 33kV SWGR, 44 bays of 13.8 kV SWGR, 2 Nos. of 380/132/13.8 kV 300/400/500 MVA Power Transformers., 2 Nos. of 132/33 kV, 80/100 MVA transformers, 3 Nos. of 132/13.8 kV, 50/67 MVA transformers, 1 no. of 380 kV, 120 MVAR bus connected reactor, 2 Nos. of 380 kV, 40 MVAR line connected reactors, 4 nos. 33 kV, 7.5 MVAR shunt capacitor banks, 3 Nos. 13.8 kV, 7 MVAR shunt capacitor banks, Auxiliary / Earthing Transformers, 380 kV & 132 kV OHTL Gantries, Control, Protection, SAS & Telecom ,Civil and MEP works.