General information

Client: Dubai Electricity & Water Authority (DEWA)
Date: Jun 2008 – Jan 2012
Task: CE/448D/2007 – Supply, Installation, Testing, Commissioning of Earth Station and International City 132kV/11kV Substations and Associated Works

Description

Turnkey Contract to Design, Supply, Install, Test and Commission 132/11kV Substations (Earth Station and International City – 4) including 132kV GIS, Power Transformers, LVAC Panels, 11kV Switchgear, Lighting, Small Power, Fire Fighting, HVAC, etc. and Associated Civil Works