General information

Client: SAVER GLASS
Date: Aug 2012 – Feb 2013
Task: E&I Installation Works for Glass Bottle Project in RAK

Description

Supply, Installation, Testing and Commissioning of LV Cables at the Saver Glass Factory from the Transformer to the Main Switchboard and from the Switchboards to Various Loads. Scope also included Supply and Installation of Cable Ladders (10 Kms) Including Equipment Installation such as MCC, Control Panels etc.